Project risks & calculation
Project risks & calculation
You are planning to make modifications to an existing application. You have identified:
30% probability of delay of receipt of resources – cost $50,000.
20% probability that the resources will be $10,000 cheaper than planned.
25% probability that there will be a problem integrating with existing software, cost to fix $3,500.
30% probability that the development may be simpler than expected, savings $2,500.
5% probability of a design defect causing $5,000 of rework.
.Calculate the net expected value for the project risks and opportunities cited above.
.How much should you plan for your contingency reserve budget based on the above?
How much would you allocate for the management reserve?
What are your assumptions about these reserves?
ORDER THIS ESSAY HERE NOW AND GET A DISCOUNT !!!
You can place an order similar to this with us. You are assured of an authentic custom paper delivered within the given deadline besides our 24/7 customer support all through.
Latest completed orders:
# | topic title | discipline | academic level | pages | delivered |
---|---|---|---|---|---|
6
|
Writer's choice
|
Business
|
University
|
2
|
1 hour 32 min
|
7
|
Wise Approach to
|
Philosophy
|
College
|
2
|
2 hours 19 min
|
8
|
1980's and 1990
|
History
|
College
|
3
|
2 hours 20 min
|
9
|
pick the best topic
|
Finance
|
School
|
2
|
2 hours 27 min
|
10
|
finance for leisure
|
Finance
|
University
|
12
|
2 hours 36 min
|